Day 1 – The windows and doors were removed.
Day 2 – The roof tiles were removed.
Day 3 – The roof timbers and asbestos shed were removed.
Day 4 – Tree branches and external walls begin to be removed.
Day 5 – All walls had been knocked down.
Day 6 – Removal of waste materials.
Day 7 – Final levelling of ground.