Demolition

Day 1 – The windows and doors were removed.



Day 2 – The roof tiles were removed.



Day 3 – The roof timbers and asbestos shed were removed.





Day 4 – Tree branches and external walls begin to be removed.





Day 5 – All walls had been knocked down.



Day 6 – Removal of waste materials.



Day 7 – Final levelling of ground.