Point of connection

We had a bit of a shock at the weekend when we noticed a rather large bracket had been mounted to the top of the garage roof.



We soon realised that this is where the point of connection will be for our 3 phase supply to the house. We could not understand why it had to be where it is. We phoned the site supervisor first thing this morning and he said this is the only place it could go to comply with Australian standards. We decided to look into it further and found out that unfortunately this is true. The problem is the point of connection has to be accessible by ladder and due to the roof above the garage door, a ladder cannot be set up to the correct angle if trying to access the top roof gable. Unfortunately you are not allowed to have the point of connection on a balcony either. The only other solution is to have a pole mounted in the corner of our block. A cable could then be run from the top of the pole to the house underground and the point of connection would then be to this pole.

We are a bit disappointed that this wasn't pointed out to us sooner and what our options were, as we could have had the pole installed sooner rather than the overhead bracket. We have decided to put up with it for now and look to get the pole installed at a later date. We will just need to make sure suitable conduit is installed underground before the driveway is laid.

Doors & Electrical fit off

We had another look inside the house today and were surprised to see all the door handles were on and the wardrobe clothes rails had been installed.









Also the electrical sockets and switches had been fitted off. They have installed standard bayonet light fittings for now in the kitchen and main living area. These will be eventually be replaced with energy saver down lights, along with the heat/extractor fan lights in the upstairs bathrooms.





The meter box is now ready for connection.

Electrical rough in

The Electrical rough in was done on Friday. This is where the Electrician runs all the cables required for power sockets, lighting and TV point. This has to be done before the walls are gyprocked, whilst there is still access.





The picture below shows where all the wires go to on the outside garage wall.



This is the meter box on the outside of the garage wall.



This picture shows where the kitchen floor has been chased out for the cables running to the island bench.



We also noticed that the ducting had been installed for the air-conditioning.