Electrical rough in

The Electrical rough in was done on Friday. This is where the Electrician runs all the cables required for power sockets, lighting and TV point. This has to be done before the walls are gyprocked, whilst there is still access.





The picture below shows where all the wires go to on the outside garage wall.



This is the meter box on the outside of the garage wall.



This picture shows where the kitchen floor has been chased out for the cables running to the island bench.



We also noticed that the ducting had been installed for the air-conditioning.