Drove past the house today and could see that the brickwork had started.
Really pleased to see they have done so much on the ground level. Hopefully the scaffolding will arrive soon so they can continue with the up stairs level.
We decided to go with a colour match mortar. It looks a little darker at the moment but should dry closer to the brick colour....we hope!
The pipework for the plumbing has been roughed in. All the water supply is done in black plastic hose instead of copper pipe these days. It looks a lot easier to install and they certainly put it in quick. Just hope we don't accidently drill into any of it in the future as it probably wouldn't take much to burst it. We might have to take plenty of pictures to show where it's all located, before the Gyprock is put up.
The picture below shows the en-suite bathroom. You can see the pipework for the bath which will be under the window.
This picture shows the drainage pipework coming down from the en-suite bathroom.
Our bricks were delivered today. We were relieved to see they were the right ones. We've heard in the past, people building with other builders have had the wrong bricks delivered and it had caused big delays.
The weather is looking good for this week so hopefully the bricklayers will crack on with it.
The bricks we have chosen are from PGH. They are the Mild Steel colour from the Matte textures range.
The framework was completed this week. Really impressed with how quick it was done. Just hope they can get the brickwork done and the roof on soon while the weather is good.