The piering was done today. Around 50 or so round holes were dug roughly 700mm deep. The depth of each hole varied depending on how firm the soil was in each spot.





As this was a provisional cost, it can vary as to how much concrete is required to fill the holes. Ours was estimated to be 35 lineal metres but ended up being 45 lineal metres. Our site supervisor told us we had been lucky, as other sites he had worked on had required as much as 50 lineal metres more than estimated.